Oakland Energy Storage Facility

Oakland Power Plant

Vistra is redeveloping its Oakland Power Plant into a 74 MW/294 MWh zero-emission energy storage facility.

The redevelopment project includes the decommissioning and demolition of the three existing fossil fuel-powered units to make room for the installation of a battery energy storage system, which will produce enough energy to power 60,000 homes for four hours.

Location (county):

Completion date:

Power capacity (in MW and MWh):

Jobs created:
Investment:

Alameda County

2025

74 MW/294 MWh

585

$91 million

Location (county):

Alameda County

Completion date::

2025

Power capacity (in MW and MWh):

74 MW/294 MWh

Jobs created:

585

Investment:

$91 million

Project milestones

Here is what is currently underway in Oakland.

2021

The two combustion turbines of Unit 2 that run on diesel fuel were decommissioned and demolished in 2021—making room on site for Phase 1 of the BESS project.

2022

Currently, the remaining Units 1 and 3 of three combustion turbines are required to operate under a Reliability Must Run (RMR) contract with CAISO, the state’s grid operator. Vistra is working with PG&E and CAISO to retire these units. Phase 2 of the BESS project may proceed once the existing units are retired and demolished.

2025

For Phase 1 of the project, we expect to have 43.25 MW/140MWh of clean energy completed by summer 2025. This part of the project will replace Unit 2.

Beyond 2025

For Phase 2 of the project, we expect to have 38.5MW/154MWh of clean energy with a completion date yet to be determined. This part of the project will replace Units 1 and 3.

Want to learn more about this project?