Oakland Energy Storage Facility

Vistra is redeveloping its Oakland Power Plant into a 74 MW/294 MWh zero-emission energy storage facility.
The redevelopment project includes the decommissioning and demolition of the three existing fossil fuel-powered units to make room for the installation of a battery energy storage system, which will produce enough energy to power 60,000 homes for four hours.
Location (county):
Completion date:
Power capacity (in MW and MWh):
Alameda County
2025
74 MW/294 MWh
585
$91 million
Location (county):
Alameda County
Completion date::
2025
Power capacity (in MW and MWh):
74 MW/294 MWh
585
$91 million
Project milestones
Here is what is currently underway in Oakland.
2021
The two combustion turbines of Unit 2 that run on diesel fuel were decommissioned and demolished in 2021—making room on site for Phase 1 of the BESS project.
2022
Currently, the remaining Units 1 and 3 of three combustion turbines are required to operate under a Reliability Must Run (RMR) contract with CAISO, the state’s grid operator. Vistra is working with PG&E and CAISO to retire these units. Phase 2 of the BESS project may proceed once the existing units are retired and demolished.
2025
For Phase 1 of the project, we expect to have 43.25 MW/140MWh of clean energy completed by summer 2025. This part of the project will replace Unit 2.
Beyond 2025
For Phase 2 of the project, we expect to have 38.5MW/154MWh of clean energy with a completion date yet to be determined. This part of the project will replace Units 1 and 3.